Optical Network Status

Since securing the right to lay underground pipelines from the state-run NETCOM in 2012, we have designed a network suited to the communication capacity of each region, centered on the 288 Core 2 line that runs through the center of Ulaanbaatar, and built an underground optical cable network of 110 km.
Through continuous network expansion to the Ger area, we have completed the construction of a 221 km optical cable network as of 2022 and completed the plan to lay additional optical cables by securing 440 km of pipelines.

Network Status

2023. 5 New pipeline installation permit drawing (total 440km)

Current status of optical cable networks built throughout Ulaanbaatar(as of May 2022)

Optical Cable Length of laying(Km)
Trunk Network
(111 Km)
288 Core 20
144 Core 23
96 Core 14
72 Core 16
36 Core 31
24 Core 7
Subscriber
Network
(110 Km)
12 Core 55
4 Core 15
2 Core 40
Total length of optical Comm network construction 221

We have completed the plan to expand the existing 221 km optical cable network, acquired the pipeline installation permit, and are currently laying advanced underground pipelines in the central area of ​​Ulaanbaatar by the end of June 2024. Once this work is completed, two sets of 288C optical cables will be laid, expanding the total optical cable network by an additional 440 km. The entire network is expected to expand as follows.

  • ⠂Total 773km optical cable network planned
    Existing 221km optical cable network
    Metro network expansion 440km
    Overhead network extension 112km
  • ⠂112km overhead optical cable network extension
    Expansion of overhead optical cable network in Ger area, a communication-vulnerable area in Ulaanbaatar, and the area of ​​​​the new Mongolian airport, Jongmod area, and the Terelj National Park area
  • ⠂Completed establishment of optical cable network construction plan for the second city (Darhan) and the third city (Erdenet)
  • ⠂Installation of base stations throughout Ulaanbaatar
    Base station installation planned for October 2025, targeting ultra-high-speed Internet wireless commercial service
    Outdoor base station 1st 480, 2nd 1,200
    Indoor AP 2,800